Project Highlight: Turnaround at GPP DINH CO – PV GAS (2022)

31/05/2025

Project Highlight: Turnaround at GPP DINH CO – PV GAS (2024)

  • Client: PV GAS – Gas Services Company

  • Location: DINH CO Gas Processing Plant (GPP DINH CO), Vietnam

  • Execution Time: 2024

  • Turnaround Duration: 12 days

Scope of Work:

The turnaround scope covered comprehensive inspection, testing, and evaluation of static equipment and piping systems in accordance with:

  • API 510 – Pressure Vessel Inspection

  • API 570 – Piping Inspection

  • API 653 – Storage Tank Inspection

The following NDT methods and advanced techniques were applied:

  • Conventional NDT: UT, RT, MT, PT, VT

  • Advanced NDT: PAUT, MFL, IRIS, RFT, ECT

  • Other services: UTM, Hydrojet Cleaning, Hardness Testing, Replica Metallography

Key Achievements:

  • Completed inspection of over 25 major equipment items within a tight 10-day shutdown window.

  • Ensured zero safety incidents and fully compliant with ASME/API standards.

  • Delivered professional reports supporting safe and timely plant re-commissioning.